School progress:
Completion of the school has been delayed until mid-July.
Timber works – timber frame and roof timber works are complete.
External walls – blockwork is complete and the slate work continues.
The stonework at the main entrance and nearing competition and stonework at the nursery wall has commenced.
Electrical sub mains has commenced in roof void and sprinkler work has also started in roof void.
Ground source – work continues on the heat pump boreholes.